SUPERINTENDENT'S REPORT FOR 2009 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Kittery Water District Consumers: |
|
|
|
|
|
|
|
| |
The District tried to do its part this past year in stimulating the
economy by contracting out some larger water main |
|
| |
replacement projects to local contractors to "put Americans back to
work" as President Obama puts it. A total of |
|
| |
9,476 feet (1.8 miles) of water main was installed in 2009; replacing
both undersize and troublesome pipe that can |
|
| |
cause emergency pipe repairs and discolored water for our consumers. A
total of 10,324 feet of old mains were |
|
| |
abandoned in place (1.95 miles). |
|
|
|
|
|
|
|
| |
The District also finalized the purchase of 60 acres of watershed land
from the former Highland Farm in York. |
|
| |
This purchase helps to protect the water quality of Boulter Pond. |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
The following is a list of the improvements that were made to the
District's system in 2009: |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Improvements / Additions to the Distribution System: |
|
|
Asset Value |
| |
|
State Road, Kittery |
|
|
|
|
|
|
|
| |
|
|
Shaw Brothers Construction installed 2,340 feet of 12" D.I.P., replaced
2 fire hydrants, |
|
|
|
| |
|
|
#68-K and #70-K, renewed 28 services and installed 1 new service. This
was phase 2 of 2. |
|
|
|
| |
|
|
(Abandoned 2,340 feet of 8" C.I.P., 30 feet of 8" D.I.P., 60 feet of 6"
C.I.P., 40 feet of 6" A/C |
|
|
|
| |
|
|
pipe and 15 feet of 2" iron pipe.) |
|
|
|
$ |
295,503.00 |
|
| |
|
Beech Ridge Road, York |
|
|
|
|
|
|
|
| |
|
|
William Shapleigh and Sons Construction installed 3,325 feet of 8" D.I.P.
and 3 fire |
|
|
|
| |
|
|
hydrants, #43-Y, #44-Y and #45-Y. |
|
|
|
|
|
| |
|
|
KWD staff renewed 63 services to complete the project. |
|
|
|
|
| |
|
|
(Abandoned 3,325 feet of 6" C.I.P.) |
|
|
$ |
280,556.00 |
|
| |
|
Sterling Road & Laurel Avenue, Kittery |
|
|
|
|
|
| |
|
|
Andrews Construction Company, Inc. installed 50 feet of 8" D.I.P., 1,511
feet of 6" D.I.P., |
|
|
|
| |
|
|
1 fire hydrant, #69-K and renewed 32 services. |
|
|
|
|
|
| |
|
|
KWD staff provided the manpower for the service renewals. |
|
|
|
| |
|
|
(Abandoned 668 feet of 6" A/C pipe, 559 feet of 4" A/C pipe and 380 feet
of 2" iron pipe.) |
$ |
169,104.00 |
|
| |
|
Pepperrell Terrace, Kittery Point |
|
|
|
|
|
|
|
| |
|
|
KWD and Ted Berry Company installed 495 feet of 4" H.D.P.E. pipe and
renewed 7 services. |
|
|
| |
|
|
(Abandoned 632 feet of 4" steel pipe and 270 feet of 2" iron pipe.) |
$ |
48,438.00 |
|
| |
|
Litchfield Road, Kittery |
|
|
|
|
|
|
|
| |
|
|
KWD installed 230 feet of 8" D.I.P. |
|
|
|
|
|
| |
|
|
(Abandoned 230 feet of 6" C.I.P.) |
|
|
$ |
34,222.00 |
|
| |
|
Dennett Road, Kittery |
|
|
|
|
|
|
|
| |
|
|
Andrews Construction Company, Inc. installed 400 feet of 6" D.I.P. and
renewed 3 services. |
|
|
|
| |
|
|
KWD staff provided the manpower for the service renewals. |
|
|
|
| |
|
|
(Abandoned 400 feet of 6" C.I.P.) |
|
|
$ |
62,195.00 |
|
| |
|
Keene Circle, Kittery |
|
|
|
|
|
|
|
| |
|
|
KWD abandoned 125 feet of 2" iron pipe by installing 5 individual
service lines. |
$ |
13,871.00 |
|
| |
|
Pleasant Street, Eliot |
|
|
|
|
|
|
|
| |
|
|
Andrews Construction Company, Inc. installed 950 feet of 8" D.I.P., 1
fire hydrant, #58-E |
|
|
|
| |
|
|
and renewed 7 services. |
|
|
|
|
|
|
|
| |
|
|
KWD staff provided the manpower for the service renewals. |
|
|
|
| |
|
|
(Abandoned 556 feet of 6" C.I.P. and 394 feet of 4" C.I.P.) |
$ |
121,974.00 |
|
| |
|
Scotland Bridge Road, York - Removal of the Former Pipe Bridge over the
York River |
|
|
|
| |
|
|
Pepperrell Cove Marine was contracted to remove the steel super
structure and dual water |
|
|
|
| |
|
|
mains that spanned over the York River. |
|
|
$ |
20,260.00 |
|
| |
|
Town of Kittery - KWD replaced fire hydrants #232-K, #162-K, #166-K, and
#167-K with 3 way |
|
|
|
| |
|
|
models. |
|
|
|
|
|
$ |
14,400.00 |
|
| |
|
Town of Eliot - KWD replaced fire hydrant #69-E with a 3 way model. |
$ |
3,600.00 |
|
| |
|
Town of York - KWD replaced fire hydrant #20-Y with a 3 way model. |
$ |
3,600.00 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
Services - 12 new, 152 renewals |
|
|
|
|
$ |
15,732.00 |
|
| |
|
Meters - 16 new |
|
|
|
|
|
$ |
5,031.00 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Treatment Plant Improvements: |
|
|
|
|
|
|
|
| |
|
Completion of the emergency standby generator replacement project |
$ |
61,616.00 |
|
| |
|
Replacement of distribution pump #1 (80% complete) |
|
$ |
26,628.00 |
|
| |
|
Continuation of hottopping the gravel driveway (Libby Scott Paving) |
$ |
10,000.00 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Facilities Improvements: |
|
|
|
|
|
|
|
| |
|
Bell Marsh Reservoir Dam |
|
|
|
|
|
|
|
| |
|
|
SUR Construction, Inc. replaced a portion of the toe drain in the dam,
installed 1 new |
|
|
|
| |
|
|
drainage inspection manhole and replaced another manhole with a new one. |
$ |
202,829.00 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Watershed Protection: |
|
|
|
|
|
|
|
| |
|
A 60 acre tract of land was purchased on the southwest shoreline of
Boulter Pond. This |
|
|
|
| |
|
purchase will allow the District to continue to protect our source of
supplies through ownership |
|
|
|
| |
|
of the adjoining lands. |
|
|
|
|
$ |
350,000.00 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
Total |
$ |
1,739,559.00 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
KWD (Kittery Water District) |
|
|
|
|
|
|
|
| |
|
D.I.P. (Ductile Iron Pipe) |
|
|
|
|
|
|
|
| |
|
C.I.P. (Cast Iron Pipe) |
|
|
|
|
|
|
|
| |
|
H.D.P.E. (High Density Polyethylene) |
|
|
|
|
|
| |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
Cost of electricity to pump 882,130,000 gallons of water
$103,965.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Water Processed in Gallons for the Year 2009 |
|
|
|
Monthly Water Processed (gallons) |
|
| |
|
Navy Base |
|
|
481,930,416 |
|
Jan |
96,677,000 |
|
| |
|
Navy Quarters-metered services |
|
9,664,160 |
|
Feb |
88,734,000 |
|
| |
|
Metered domestic services |
|
226,465,228 |
|
Mar |
95,316,000 |
|
| |
|
Metered commercial services |
|
41,092,128 |
|
Apr |
87,438,000 |
|
| |
|
Metered municipal services |
|
15,788,036 |
|
May |
61,375,000 |
|
| |
|
Metered industrial services |
|
31,445,920 |
|
Jun |
52,753,000 |
|
| |
|
Balance, Metered & Un-metered |
|
75,744,112 |
|
Jul |
51,439,000 |
|
| |
Total Water Processed |
|
882,130,000 |
|
Aug |
58,935,000 |
|
| |
|
Average Daily Water Processed |
|
2,416,795
|
|
Sep |
54,006,000 |
|
| |
|
|
|
|
|
|
|
Oct |
76,780,000 |
|
| |
|
|
|
|
|
|
|
Nov |
74,263,000 |
|
| |
|
|
|
|
|
|
|
Dec |
84,414,000 |
|
| |
|
|
|
|
|
|
|
Total Water Processed |
882,130,000 |
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
 |
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Respectfully submitted, |
|
|
|
|
|
|
|
|
|
Michael S. Rogers |
|
Superintendent |
|
Kittery Water District |
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|